Testing is typically performed post second fix.

All major penetration to walls and floors must have already been made.

On top of this, you’ll need:

  • All service penetrations sealed
  • Trickle vents installed
  • Loft access hatch in place
  • Plumbing complete with water in the traps
  • Seals fitted on external doors
  • Electrical outlets fitted